Constraint-led specification
The deciding factor was not drive performance but physical fit. Panel space, existing gland plates and cable lengths determined what could be installed within the outage, so those constraints were surveyed before any product was selected.
Configuration before delivery
Each drive was supplied with the station parameter set already loaded and verified, removing the single largest source of commissioning delay on a job of this type.
Staged delivery
Panel modification components arrived ahead of the drives so fabrication work could be completed in advance, leaving only mechanical replacement and commissioning inside the outage itself.